On November 6th, construction works were completed, creating a new recreational area in the district of Nowa Wieś. The investment included the construction of a parking lot, sidewalks, a roundabout, bicycle racks, trash bins, a sandbox, seesaws, swings, a carousel, play sets, and a table with seating. The fire-fighting tank was also removed. The cost of this project was 210,403.00 PLN. The City Hall of Myszków, in designing the park in Nowa Wieś, included in the project documentation the partial demolition of the fire-fighting tank, as evidenced by the measurements of the works, which are part of it.
In order to reduce the costs of the project, it was initially planned that the rubble to fill the tank would come from the demolition of concrete elements from other municipal buildings. Therefore, the tank was filled immediately after the rubble was transported.
In the future, a recreational court for volleyball and basketball is planned for the area of the tank. The area for the court will be drained to the depth of the demolished tank.