Construction of the artificial turf field, which started at the beginning of October, will be completed on November 28, 2008.
The works are carried out by the company BUD – WOD – Bis from Katowice.
The cost of the investment has not changed and amounts to 832,177.22 Polish zlotys.
As of today, the following works have been completed:
1. dismantling works (works related to shaping sports and recreational areas)
2. earthworks (works related to shaping sports and recreational areas)
Currently ongoing works:
1. drainage (drainage works)
2. substructure (construction works related to building sports fields)
Works needed to finalize the construction:
1. sidewalk with concrete cobblestones
2. fencing
3. turf field surface (construction works related to building sports fields)
4. finishing works