The field is close.

Construction of the artificial turf field, which started at the beginning of October, will be completed on November 28, 2008.

The works are carried out by the company BUD – WOD – Bis from Katowice.

The cost of the investment has not changed and amounts to 832,177.22 Polish zlotys.

As of today, the following works have been completed:
1. dismantling works (works related to shaping sports and recreational areas)
2. earthworks (works related to shaping sports and recreational areas)

Currently ongoing works:
1. drainage (drainage works)
2. substructure (construction works related to building sports fields)

Works needed to finalize the construction:
1. sidewalk with concrete cobblestones
2. fencing
3. turf field surface (construction works related to building sports fields)
4. finishing works